Milestones

The Joomla Accessibility Project is organised into 20 milestones, covering the full journey from the initial audit and remediation through design, administration, testing, documentation, and final validation. The overview below shows the current status of each milestone.

MilestoneAreaStatus1)Publish Date2)
1aExpert Audit and Baseline Metrics✅ Completed18.05.2026
1bRemediation Plan, Quick Wins and Community Publication🟡 In progress15.07.2026
2aDesign System, Tokens and Core Components🟡 In progress10.08.2026
2bDesign System – Complex Components & Validation🟠 Selection process10.08.2026
3aFrontend Template Build⚪ Not yet open02.01.2027
3bBackend Template Build⚪ Not yet open02.01.2027
3cFramework-agnostic Templates⚪ Not yet open02.01.2027
4Accessible Sample Dataset⚪ Not yet open01.07.2027
5aConfigurable Authoring Forms – Backend System⚪ Not yet open01.03.2027
5bConfigurable Authoring Forms – Accessible UI & Documentation⚪ Not yet open01.03.2027
6aStandardized Batch⚪ Not yet open16.11.2026
6bFilter in Administration⚪ Not yet open10.06.2027
7aTransversal Features – Audit & Documentation🟡 In progress12.08.2026
7bTransversal Features – Standardisation Phase 1🟠 Selection process12.08.2026
7cTransversal Features – Standardisation Phase 2🟠 Selection process12.08.2026
8aAutomated Accessibility Testing in CI – Core Tests & CI Gate🟡 In progress14.08.2026
8bAutomated Accessibility Testing in CI – Dashboard & Extension Guide🟡 In progress14.08.2026
9aDeveloper Documentation – Guide & Reference Pages⚪ Not yet open01.06.2027
9bDeveloper Documentation – Community Sessions & Finalization⚪ Not yet open01.06.2027
10External Audit, Finalization & Handover⚪ Not yet open01.09.2027

1) States:

⚪ Not yet open

🔵 Call open

🟠 Selection process

🟡 In progress

✅ Completed

2) Published Date

Expected publish date for the call to submit RFPs. Calls will be published on the OSM Website